Down payments made;
Ayub- Kshs 15,000 for hanging baskets and benches
Mark Carpenter - Kshs 14,500 for KACH benches balance 3,900 with Silas to be paid when work is completed.
Jared - Basket ball court payment Kshs 5,000
Benard and Simon Kshs 4,500 for passion plants and passion trellis.
Work in progress as per Lisa's specifications.
First aid quote Kshs 9,000
Tuesday, March 23, 2010
Thursday, March 18, 2010
WOW!!! This is known as PROGRESS!!! ASANTE!!!
Habari Silas,
You have been at WORK!!! Great job. This is a fabulous way to communicate about IPI-Kenya's projects - i am so very impressed. I cannot wait to see what new things are coming up at KACH - we are a great opportunity and possibility for transformation in our nation. Indeed, we inspire action for peace all around: in us, with others and among us. We are not only transforming KACH physically but also spiritually, economically and mentally: one child at a time. This means we must transform the lives of orphans and vulnerable children at IPI-Kenya (and adults too) so that they excel in their lives - and we are getting there!!! TOGETHER as a team, we are firmly marching to our destination: A new way to care for and support of orphans and vulnerable children in our communities.
Keep up the great work. Thank you for all you have done!!
Amani.
Karambu
You have been at WORK!!! Great job. This is a fabulous way to communicate about IPI-Kenya's projects - i am so very impressed. I cannot wait to see what new things are coming up at KACH - we are a great opportunity and possibility for transformation in our nation. Indeed, we inspire action for peace all around: in us, with others and among us. We are not only transforming KACH physically but also spiritually, economically and mentally: one child at a time. This means we must transform the lives of orphans and vulnerable children at IPI-Kenya (and adults too) so that they excel in their lives - and we are getting there!!! TOGETHER as a team, we are firmly marching to our destination: A new way to care for and support of orphans and vulnerable children in our communities.
Keep up the great work. Thank you for all you have done!!
Amani.
Karambu
Financial meeting with AI
Meeting with AI
3/18/10
Participants: Silas, Kathy, Lisa, Jared
Summary of Discussion:
Dining Hall/ Local Contractor-JARED:
DINING HALL:
Status: foundation and walls complete
Paid work:$5000.00 USD
needed to complete: $14,666.00 USD ( 1,100,000.00 KSH)
Canopy for veranda( metal posts and same metal framing as on KACH windows): awaiting quote
payment needed to complete roof and ceiling is $5000.00
BB COURT:
Paid: $1500.00 usd
owed:$50,000 KSH
basket ball ring:$ 1000 KSH ( we have one paid for we need another)
Post: awaiting quote
work needed to complete:
wall: $5000 KSH
path:$ 25,000 KSH9 awaiting dirt from veranda construction
GARDEN: work to be completed by simon and bernard
passion trellis: $ 4200 KSH
passion plants: $300 KSH
Paid by Lisa
upper orchard:$ 100 KSH mulberry
paid by lisa
First aid kit:$
supplies(gumboots, jackets, gloves, hosepipe, sprinklers): $ 20,500.00 KSH
paid by lisa
LANDSCAPE: AYUB: silas to give ayub deposit and see work is complete in two weeks
AI to pay 77,000 KSH owed by IPI for work completed 7/09
Benches: 19,500 KSH
Hanging baskets: 13,800 KSH
Deposit: 15,000 KSH
KACH:
paint and improvements( murals, and art supplies):+/- 3600 KSH
Furniture: completed by 4/15 ( 5 benches tables wait until dining hall is complete then do one table prototype to see if like it. all info is in IPI office)
Benches( designed by lisa and provided by mark carpenter):$3680/piece X5 approx $250.00 usd- paid by lisa
tables:$ 6240/ per table
3/18/10
Participants: Silas, Kathy, Lisa, Jared
Summary of Discussion:
Dining Hall/ Local Contractor-JARED:
DINING HALL:
Status: foundation and walls complete
Paid work:$5000.00 USD
needed to complete: $14,666.00 USD ( 1,100,000.00 KSH)
Canopy for veranda( metal posts and same metal framing as on KACH windows): awaiting quote
payment needed to complete roof and ceiling is $5000.00
BB COURT:
Paid: $1500.00 usd
owed:$50,000 KSH
basket ball ring:$ 1000 KSH ( we have one paid for we need another)
Post: awaiting quote
work needed to complete:
wall: $5000 KSH
path:$ 25,000 KSH9 awaiting dirt from veranda construction
GARDEN: work to be completed by simon and bernard
passion trellis: $ 4200 KSH
passion plants: $300 KSH
Paid by Lisa
upper orchard:$ 100 KSH mulberry
paid by lisa
First aid kit:$
supplies(gumboots, jackets, gloves, hosepipe, sprinklers): $ 20,500.00 KSH
paid by lisa
LANDSCAPE: AYUB: silas to give ayub deposit and see work is complete in two weeks
AI to pay 77,000 KSH owed by IPI for work completed 7/09
Benches: 19,500 KSH
Hanging baskets: 13,800 KSH
Deposit: 15,000 KSH
KACH:
paint and improvements( murals, and art supplies):+/- 3600 KSH
Furniture: completed by 4/15 ( 5 benches tables wait until dining hall is complete then do one table prototype to see if like it. all info is in IPI office)
Benches( designed by lisa and provided by mark carpenter):$3680/piece X5 approx $250.00 usd- paid by lisa
tables:$ 6240/ per table
Welcome
Welcome to our new communication. Here we will post agendas, meeting minutes, pictures etc...
we look forward to sharing with you!